安(ān)裝(zhuāng)示意(yì)图(tú)1
折彎方通(tòng)天(tiān)花(huā)吊頂(配平齒龍骨(gǔ))安(ān)裝(zhuāng)说(shuō)明(míng):
1.按設計(jì)要求测出(chū)安(ān)裝(zhuāng)後(hòu)的(de)标高(gāo);
2.确定(dìng)施工方向(xiàng),按≤1200mm距離在(zài)建築結構天(tiān)花(huā)上(shàng)打(dǎ)好(hǎo)吊裝(zhuāng)孔,用(yòng)膨脹螺栓固定(dìng)吊杆;
3.固定(dìng)轻鋼(gāng)龍骨(gǔ)吊件(jiàn)、轻鋼(gāng)龍骨(gǔ),将轻鋼(gāng)龍骨(gǔ)調至(zhì)水(shuǐ)平同(tóng)时(shí)調整好(hǎo)轻鋼(gāng)龍骨(gǔ)的(de)标高(gāo),每条(tiáo)龍骨(gǔ)相互平行;
4.用(yòng)条(tiáo)扣吊件(jiàn)将平齒龍骨(gǔ)固定(dìng)在(zài)轻鋼(gāng)龍骨(gǔ)上(shàng),調整好(hǎo)水(shuǐ)平,平齒龍骨(gǔ)必须要彼(bǐ)此(cǐ)平行且(qiě)垂直(zhí)于(yú)轻鋼(gāng)龍骨(gǔ);
5.安(ān)裝(zhuāng)方型扣闆:将折彎方通(tòng)扣入(rù)平齒龍骨(gǔ)槽中(zhōng)即可(kě);
6.收(shōu)邊(biān)處(chù)應(yìng)根(gēn)據(jù)現(xiàn)场情(qíng)況量(liàng)取(qǔ)尺(chǐ)寸(cùn),将天(tiān)花(huā)闆搭在(zài)收(shōu)邊(biān)角(jiǎo)上(shàng)。
7.安(ān)裝(zhuāng)过程應(yìng)保持(chí)手(shǒu)清(qīng)潔,不(bù)能(néng)有(yǒu)汗水(shuǐ)、油(yóu)污等不(bù)良現(xiàn)象(xiàng)

安(ān)裝(zhuāng)示意(yì)图(tú)2
組合式折彎方通(tòng)天(tiān)花(huā)吊頂(配豎齒方通(tòng)龍骨(gǔ))安(ān)裝(zhuāng)说(shuō)明(míng):
1.按設計(jì)要求测出(chū)安(ān)裝(zhuāng)後(hòu)的(de)标高(gāo);
2.确定(dìng)施工方向(xiàng),按≤1200mm距離在(zài)建築結構天(tiān)花(huā)上(shàng)打(dǎ)好(hǎo)吊裝(zhuāng)孔,用(yòng)膨脹螺栓固定(dìng)吊杆;
3.固定(dìng)轻鋼(gāng)龍骨(gǔ)吊件(jiàn)、轻鋼(gāng)龍骨(gǔ),将轻鋼(gāng)龍骨(gǔ)調至(zhì)水(shuǐ)平同(tóng)时(shí)調整好(hǎo)轻鋼(gāng)龍骨(gǔ)的(de)标高(gāo),每条(tiáo)龍骨(gǔ)相互平行;
4.用(yòng)条(tiáo)扣吊件(jiàn)将平齒龍骨(gǔ)固定(dìng)在(zài)轻鋼(gāng)龍骨(gǔ)上(shàng),調整好(hǎo)水(shuǐ)平,平齒龍骨(gǔ)必须要彼(bǐ)此(cǐ)平行且(qiě)垂直(zhí)于(yú)轻鋼(gāng)龍骨(gǔ);
5.安(ān)裝(zhuāng)方型扣闆:将折彎方通(tòng)扣入(rù)平齒龍骨(gǔ)槽中(zhōng)即可(kě);
6.收(shōu)邊(biān)處(chù)應(yìng)根(gēn)據(jù)現(xiàn)场情(qíng)況量(liàng)取(qǔ)尺(chǐ)寸(cùn),将天(tiān)花(huā)闆搭在(zài)收(shōu)邊(biān)角(jiǎo)上(shàng)。
7.安(ān)裝(zhuāng)过程應(yìng)保持(chí)手(shǒu)清(qīng)潔,不(bù)能(néng)有(yǒu)汗水(shuǐ)、油(yóu)污等不(bù)良現(xiàn)象(xiàng)。